Product: X12 EDI
Transaction: 806
FUNCTIONAL GROUP=PJ
This X12 Transaction Set contains the format and establishes the data contents of the Project Schedule Reporting Transaction Set (806) for use within the context of an Electronic Data Interchange (EDI) environment. This transaction set provides for the transmission of planning, scheduling, and status information. The purpose of this transaction set is to establish an initial plan, report progress against the plan, and report changes to the plan. It is designed to serve the needs of government agencies, prime contractors and their subcontractors.
SCHEMA
ST
Segment | Name | Position |
ST | 0100 | |
BPP | Beginning Segment for Project Schedule Reporting | 0200 |
REF | 0300 |
N1
Segment | Name | Position |
N1 | 0400 | |
N2 | 0500 | |
N3 | 0600 | |
N4 | 0700 | |
REF | 0800 | |
PER | 0900 | |
DTM | 1000 |
CAL
Segment | Name | Position |
CAL | Calendar | 0100 |
QTY | 0200 | |
DTM | 0300 |
RSC
Segment | Name | Position |
RSC | Resource | 0400 |
REF | 0500 | |
DTM | 0600 | |
QTY | 0700 | |
AMT | 0800 | |
PCT | Percent Amounts | 0900 |
RPA | Rate Amounts or Percents | 1000 |
TID
Segment | Name | Position |
TID | Task Identification | 1100 |
REF | 1200 | |
DTM | 1300 | |
QTY | 1400 | |
AMT | 1500 | |
PCT | Percent Amounts | 1600 |
N1 | 1700 | |
PER | 1800 | |
PID | 1900 |
MTX
Segment | Name | Position |
MTX | 2010 | |
DTM | 2020 | |
NM1 | Individual or Organizational Name | 2030 |
REF | 2040 |
RSC
Segment | Name | Position |
RSC | Resource | 2100 |
REF | 2200 | |
DTM | 2300 | |
QTY | 2400 | |
AMT | 2500 | |
PCT | Percent Amounts | 2600 |
RPA | Rate Amounts or Percents | 2700 |
PAM | Period Amount | 2800 |
MLS
Segment | Name | Position |
MLS | Milestone | 2900 |
REF | 3000 | |
DTM | 3100 | |
QTY | 3200 | |
AMT | 3300 | |
PCT | Percent Amounts | 3400 |
SE
Segment | Name | Position |
SE | Transaction Set Trailer | 3500 |